Building Update – 19 November 2021

The ATU (Aerated/Aerobic Treatment Unit, i.e. wastewater treatment system) was installed today. Pending power and plumbing connections, it will be ready for use. This link shows a time lapse of today’s installation.

On the plasterboard front, we’re still waiting for additional assistance to install them. What we’ve found is that we can installed up to 3m length plasterboard with the lifter and various tools we’ve purchased, 4.8m sheets are still a challenge. Our neighbour should be able to provide assistance next weekend, at least for the first 3 rows of the ceiling board so that we don’t further hold up the garage door installation.